The Collingham Project

The Project: Two storey extension and reconfiguration of a three bedroom, detached property in Collingham, Wetherby.

My Role: Spatial planning, interior design concepts, detailed design, bespoke joinery design, lighting design, specification, project support, liaising with trades, final styling

Timeframe: Initial consultation - July 2021. Planning Approved - November 2021. Build - July 2022 - Feb 2023. Project Completion - October 2023.

£: 35 days plus initial consultation

Architecture - Niche Design Architects Photography - Katie Lee
År for projekt: 2023
Projektomkostninger: 75.001 - 100.000 GBP
Land: Storbritannien